Kinsmen Arena Ice Systems Upgrades

The City of Yorkton is undertaking a renovation project at the Kinsmen Arena to extend the longevity of the ice systems for future years. Approved as part of the 2023, 2024, and 2025 capital budgets, this project will entail:

  • The removal of the existing rink system, including boards, glass, player benches, spectator seating, and the concrete arena floor.
  • Removal and replacement of the ground soils, forming a strong, solid base for the new arena slab floor.
  • Installation of new rink systems, including the concrete arena floor (complete with new refrigeration piping), new rink boards, arena glass, player benches, spectator seating, and other arena amenities.
  • Installation of dehumidification for the arena
  • Code and ice plant upgrades

This project was approved and funding allocated following the Gallagher Centre Renewal Project, and in addition to the Westland Arena Ice Plant Upgrades Project, which was completed in 2023.


Subscribe to this project page to stay up to date on the work happening as part of the Kinsmen Arena Ice Systems Upgrades!

The City of Yorkton is undertaking a renovation project at the Kinsmen Arena to extend the longevity of the ice systems for future years. Approved as part of the 2023, 2024, and 2025 capital budgets, this project will entail:

  • The removal of the existing rink system, including boards, glass, player benches, spectator seating, and the concrete arena floor.
  • Removal and replacement of the ground soils, forming a strong, solid base for the new arena slab floor.
  • Installation of new rink systems, including the concrete arena floor (complete with new refrigeration piping), new rink boards, arena glass, player benches, spectator seating, and other arena amenities.
  • Installation of dehumidification for the arena
  • Code and ice plant upgrades

This project was approved and funding allocated following the Gallagher Centre Renewal Project, and in addition to the Westland Arena Ice Plant Upgrades Project, which was completed in 2023.


Subscribe to this project page to stay up to date on the work happening as part of the Kinsmen Arena Ice Systems Upgrades!

  • Project Update

    February 11, 2025

    Sandblasting within the Kinsmen Arena is continuing, however is a lengthy, dusty process! Images below show the progress made so far, and we expect this to continue for a few more weeks until finished. Once completed, the sand and paint debris will be collected and disposed of properly, after which the project will shift to demolition of the concrete floor and excavation of ground materials.


  • Project Update - Kinsmen Club of Yorkton Donation

    At a media event held on January 27th, the Kinsmen Club of Yorkton announced a donation to the Kinsmen Arena project. Ron Hanishewsky, President of the Kinsmen Club presented Mayor Aaron Kienle with a cheque for $220,000.00 towards the replacement of the arena boards and glass. In a statement, Mr. Hanishewsky said that "The Club's donation to the project will ensure the arena remains a key venue for sports and recreational activities for future generations."

    Additional details can be found on the Kinsmen Club of Yorkton's Facebook page at https://www.facebook.com/YorktonKinsmen, and on the City's News and Notices webpage at https://www.yorkton.ca/Modules/News/en.

    The City of Yorkton truly appreciates this contribution from the Kinsmen Club!

    Photo courtesy of Kinsmen Club of Yorkton.

  • Project Update

    January 20, 2025

    Tear down and removal of items continues at the Kinsmen Arena. The rink boards, arena glass and stanchions, player benches, spectator seating, protective netting, and other amenities have been removed as work progresses. Up next is sandblasting and the safe removal and abatement of lead paint from in side the arena area, before we move into demolition and excavation of the concrete arena floor and base materials.


  • Project Update - Construction Begins

    January 6, 2025

    Things look a little bit different around the Kinsmen Arena! After a very successful Paint the Ice event on December 23rd, staff worked over the holidays to remove the ice from the rink to prepare things for PCL Construction to move in. Currently, work is being done to remove the arena glass, which will be followed by removal of the rink boards, bleacher seating, and other amenities within the arena. Subscribe to this page to stay up to date with the Kinsmen Arena project!

  • FAQs

    What is being completed during this project?

    The Kinsmen Arena Ice Systems Upgrades Project will see replacement of the concrete slab (including all the refrigeration piping), new arena boards and glass, arena dehumidification and code and safety upgrades in the plant room. The project will also address some spectator experience items including new bleacher seating complete with accessible seating areas, replacement of the safety netting surround the ice surface, new sound system, and other improvements.


    Why are the dressing rooms not being renovated? Why is the rink not being twinned as part of the project?

    The intent of the project is to ensure that the ice plant and related mechanical/building systems can support ice for the next 15 years. Renovations to the dressing rooms and lobby areas were not included in the scope of the project.

    Twinning of an ice surface was the focus of the Gallagher Centre Renewal Project in 2019 which did not proceed.


    Why did the City decide to shut the Kinsmen down in the middle of the hockey season? Why doesn’t the project happen when the rink is closed during the summer?

    The Kinsmen Arena project is scheduled to take up to 9 months to complete, and would have an impact on the hockey season regardless of when it starts. The City and Yorkton Minor Hockey worked together to determine when would be the best time to close the rink, and landed on a January start date for the closure and start of the project.


    When is the last day for skating at the Kinsmen Arena?

    December 23 is the planned last day for skating.


    When will the rink re-open?

    The project is anticipated to be completed in time for the rink to open in September 2025 for the next hockey season.


    I heard the project costs over $12 million dollars. Why does it cost so much?

    The approved budget for the project is $4,500,000.00, not including GST:

    • Project Cost - $3,925,615.66
      • Removal of existing boards, glass, concrete slab, and excavation of ground materials
      • New ground materials to build solid foundation and base
      • New concrete slab, complete with refrigeration piping
      • New rink boards, glass, player benches, and spectator amenities
      • New arena dehumidification system
      • Code requirements, safety, and mechanical upgrades within the arena ice plant room
    • Spent to Date - $215,561.86
    • Project Insurance - $34,980.00
    • Project Contingency - $328,055.00 (only if required)

    How much are taxes increasing because of this project?

    This project does not have an impact on taxes. The Kinsmen Arena project is internally funded by the annual Recreation Levy through 2030, becoming available for the 2031 budget cycle.

  • Project Status Update

    July 29, 2024 – Project Awarded

    Following the July 8th Council meeting, the City’s project team, representatives from Alton Tangedal Architect (the project consultants) and project personnel from PCL Construction met to begin reviewing options to reduce the scope of work and overall project budget. The primary focus was on cosmetic items, including sandblasting and painting, blue room rubber flooring, protective netting, ceiling patching, and the arena sound system. Further investigation into refrigeration system adjustments, electrical and mechanical revisions, and potential changes to the dehumidification system was completed, however substantial cost savings were unable to be identified. A direct connection between the City and PCL’s internal insurance division was also made in order to explore project insurance options and costing.

    Potential changes to the project scope and budget savings was presented to Council at the July 29, 2024 Council meeting, and while approximately $130,000.00 in savings was identified it was decided to proceed with awarding the project to PCL Construction as originally tendered. As many of the proposed project changes would be required in the near future, City Council was unanimous in including these items in the overall project now, saving on future costs, down times, and potential impact to operations.

    The Kinsmen Arena Ice System Upgrades project has been awarded to PCL Construction Management Inc., with a contract cost of $3,925,615.66, including PST and excluding GST. Construction on the project is scheduled to begin in January 2025, and be completed by September 2025, in time for the start of the 2025-2026 ice season.

    The Kinsmen Arena will operate normally from September through December of 2024.

  • Project Status Update

    July 8, 2024 - Notice of Intent to Award

    Tender bids for the Kinsmen Arena Ice Systems Upgrade project were presented to City Council at the regular Council meeting on Monday, June July 8, 2024. Three bids were received, and Council has authorized Administration to proceed with issuing an “Intent to Award” notice to PCL Construction Management Inc. The Intent to Award notice allows the City and the contractor to review the project and propose revisions to the scope of work in an effort to reduce the overall project budget. A follow up report on the Kinsmen Arena Ice Systems Upgrade Project will be presented to City Council at the July 29, 2024 meeting.

  • Project Status Update

    June 13, 2024 - Project is out for Tender

    The design for the ice system upgrade has been completed and the project is currently out for tender. The tender results will be presented to City Council in July 2024. If the project is approved to proceed construction will begin in January 2025 with the goal of being completed by the start of the 2025-2026 ice season. The Kinsmen Arena will operate as normal from September through December 2024.

  • Boring for Geo-technical Sampling Complete

    April 4, 2023

    Contractors were on site at the Kinsmen Arena and obtained geo-technical soil samples to inform the Kinsmen Arena Ice Systems Upgrade Project. These samples will be studied to determine the soil composition underneath the rink which, will be used to determine how much excavation will be required as part of the arena slab replacement. This work involved drilling holes through the concrete floor and brine lines to gather the samples. The brine lines and concrete will be repaired this summer to allow the Kinsmen to open again for the regular 2023-2024 season.


  • Kinsmen Arena Ice Systems Upgrade

    January 2023 - Consultants Engaged

    The City is now proceeding with the Kinsmen Arena Upgrades Project, and has engaged Alton Tangedal Architect LTD from Regina to lead a team of consultants to design and coordinate the work required at the Kinsmen Arena, as approved by City Council:

    Structural Engineering: Brownlee Beaton Kreke,

    Mechanical Engineering: RJ England Consulting Ltd

    Electrical Engineering: Rittenburg and Associates Ltd

    Refrigeration Engineering: Accent Refrigeration Systems

    Geotechnical Engineering: Clifton and Associates

    February 2023 - Planning Discussion with Yorkton Minor Hockey

    Members of the City’s project team met with representatives from Yorkton Minor Hockey to begin conversations on project implementation and timelines. The Kinsmen Arena is the primary home of Yorkton Minor Hockey programming, and as such there will be significant impact to hockey programming during project construction. It is anticipated that the Kinsmen Upgrades Project could take up to 10 months to complete, and it was important that Administration and Yorkton Minor Hockey take a proactive and collaborative approach to planning the project to minimize the impact to operations to the best ability. Preferred project timelines and implementation dates were provided by Yorkton Minor Hockey and will be shared with the project consultants and further planning and project design continue.

    March/April 2023 - Geotechnical Study

    A geotechnical survey of the ground conditions underneath the arena slab is planned for April 2023, once the ice has been taken out at the end of the season. This survey will further inform the project timeline planning, as it will assist with identifying how much excavation is required as part of the arena slab replacement.