Cold Floor Piping Complete

  • The cold floor piping has now been installed.
  • A layer of metal mesh reinforcement will be placed next.
  • The concrete pour is scheduled for August 12, and is expected to take approximately 10 to 12 hours to complete.
  • Following the pour, the slab will undergo a 28-day curing period before the next phase of work begins, however other work will continue to progress while we wait.