Deer Park Golf Course Clubhouse Project

Consultation has concluded

In 2019 the City of Yorkton conducted an Indoor Recreation Facility feasibility study with aodbt Architecture and Interior Design. In addition to the replacement of the Kinsmen Arena, the Deer Park Clubhouse was also identified as being a facility that has reached, or is nearing, the end of its useful life. After approving a general concept plan, and location for a possible new clubhouse at Deer Park at their October 26, 2020 Council meeting, City Council tasked Administration to work with aodbt Architecture and Interior Design to take the approved concept plan through to 100% design. The proposed new clubhouse includes water and sewer services as well.

Public questions and feedback were presented to Council, along with the final design and preliminary cost at the October 25, 2021 Council Meeting for Council consideration to decide whether to proceed to tender. The new Clubhouse was approved at the January 31, 2022 Council Meeting with a budget of $7.6 million.

The new Deer Park Clubhouse has a total capacity of 200 persons. This is when the restaurant, covered deck and patio are in use.

The breakdown is as follows:

  • Restaurant - 80 people
  • Covered deck - 80 people
  • Patio - 40 people

In 2019 the City of Yorkton conducted an Indoor Recreation Facility feasibility study with aodbt Architecture and Interior Design. In addition to the replacement of the Kinsmen Arena, the Deer Park Clubhouse was also identified as being a facility that has reached, or is nearing, the end of its useful life. After approving a general concept plan, and location for a possible new clubhouse at Deer Park at their October 26, 2020 Council meeting, City Council tasked Administration to work with aodbt Architecture and Interior Design to take the approved concept plan through to 100% design. The proposed new clubhouse includes water and sewer services as well.

Public questions and feedback were presented to Council, along with the final design and preliminary cost at the October 25, 2021 Council Meeting for Council consideration to decide whether to proceed to tender. The new Clubhouse was approved at the January 31, 2022 Council Meeting with a budget of $7.6 million.

The new Deer Park Clubhouse has a total capacity of 200 persons. This is when the restaurant, covered deck and patio are in use.

The breakdown is as follows:

  • Restaurant - 80 people
  • Covered deck - 80 people
  • Patio - 40 people
Consultation has concluded
  • Power installation

    supporting image

    Power is being installed this week. This includes a new power pole, transformer and directional boring of the line from one to the other.

    You need to be signed in to add your comment.

  • Clubhouse structure making progress

    supporting image

    The steel columns for the Super Structure are being erected.

    You need to be signed in to add your comment.

  • Concrete for foundation complete, floor framing in progress

    supporting image

    The concrete portion of the foundation is complete! This stage of constructions creating typical crawl space under a building. The internal fill has been installed and sloped for drainage with a layer of sand over. A permalon radon barrier will be installed later.

    Floor framing has started with concrete and (LVL) Laminated veneer lumber beams on top of concrete columns and floor trusses being installed on top, sub-floor will follow shortly. Once these steps are complete, the exterior of the foundation will be backfilled to the height of the ridged pink insulation.

    You need to be signed in to add your comment.

  • Curb construction for permanent parking lot

    The north parking area will be closed on Monday, August 29th to begin curb construction for the permanent parking lot. We ask the public to find alternative parking closer to the Pro Shop Trailer for the time being. We apologize for the inconvenience.

    The ramp and east entrance to the Pro Shop Trailer will also be closed next week to allow for curb construction to begin in the parking lot. Access to the Pro Shop trailer will be through the west entrance at this time.

    You need to be signed in to add your comment.

  • Building foundation in progress

    supporting image

    In the attached photo you can see a foundation which creates a typical crawl space under a building to house the ducting for the HVAC as well as the plumbing and electrical runs. There will also be a mechanical room housing the mechanical and electrical equipment. The space will not be filled completely with sand, there will be some fill installed to taper the inside slope for drainage and then the installation of a permalon radon barrier.

    You need to be signed in to add your comment.

  • Pouring Concrete

    There will be an increase in traffic at the Deer Park Clubhouse Construction Site on Tuesday, August 2. Concrete trucks will be on site throughout the day. A Pump Truck will be on site at approximately 12:30 p.m. and will be set up in the south west corner of the construction site behind the Temporary Pro Shop. Visitors to the golf course will see concrete trucks utilizing the path behind the pro shop. An individual will be in the area directing traffic and to ensure the safety of golf course users and staff during this time.

    You need to be signed in to add your comment.

  • Parking Adjustments

    supporting image

    Effective Monday, July 11, 2022 the Deer Park Golf Course Parking Lot will be adjusting its parking plan in order to move further along with the construction of the Deer Park Clubhouse. This parking plan will remain until the construction is completed. Construction fencing will be rearranged along with some of the construction trailers on site. The construction site will be be busy during this transition time, so we ask everyone for their patience when in the area and to move about the parking lot and pro shop with caution.

    You need to be signed in to add your comment.

  • Crane at the Deer Park Clubhouse

    There will be a crane at the Deer Park Clubhouse on Thursday, June 23 (and possibly into Friday, June 24).
    Vehicles will be accessing the road on the west side of the Clubhouse. Please use caution when you are near the construction area of the Clubhouse. Traffic will increase at approximately 7 a.m. and will be steady throughout the day. Park in designated areas to not interfere with the traffic flow of construction vehicles, The back tee on Hole 1 will be closed during the time and the front tee will remain open.

    You need to be signed in to add your comment.

  • Deer Park Clubhouse Demolition

    Demolition of the old Deer Park Clubhouse began on Monday, April 4, 2022 and was completed on Wednesday, April 13, 2022. Site clean up was completed following the excavation of the foundations of the former clubhouse.

    The material excavated will be used as backfill once the new foundation is complete.

    You need to be signed in to add your comment.