York Road Construction Project: September Update

Phase 5 of the York Road construction project is now approximately 85% complete!

Here's the latest progress:

Concrete Work: has been successfully wrapped up.

Upcoming Work:

The base material is scheduled to be finished by the week of September 30 and commence paving later in the week. We’re on track!

Finish clean-up and landscaping tasks.

Line painting will follow promptly after the paving is complete, ensuring clear, safe driving lanes.

The above is all weather dependent.