Project Update - Sandblasting Complete

Sandblasting work has wrapped up in the Kinsmen Arena. This tedious process saw the removal and abatement of lead paint through the arena area, including on all the support beams which go across the ice surface.This lead paint removal process required additional safety and remediation practices to ensure the safety of those working within the building.

Work inside the arena has now transitioned to high-level and support beam painting, as well as re-installation of ceiling insulation. These items are being completed now to minimize any paint overspray and the need to do finishing work once the new ice slab has been installed. The project is on track to start concrete demolition and removal in the coming weeks.

In addition to the sandblasting and painting within the arena area, work has been progressing in the ice plant and electrical areas of the facility, including renovations to piping and refrigeration systems in preparation of new equipment. The new arena chiller was also delivered, ensuring it is on site and ready to go for installation in the coming months. Flooring in the Blue Room has also been removed and remediated in preparation of the new rubber flooring being installed.


#<Object:0x00000000253c2d30>