Drying Things Out

The sump pits and water pumping has greatly improved the conditions within the arena area. Large fans have also been installed to assist with drying out the materials, and excavation is continuing with the dryer material. On the outside, the ground materials and existing slab are starting to be hauled away. In the ice plant room, the new chiller and some connection piping has been installed.

#<Object:0x0000000033c2e150>