June 12 Progress Update
- Phase 1 (Dalebrooke and Broadway intersection) undergrounds and roadway work were 100% completed as of May 20th.
- SaskEnergy completed the gas main relocation work on June 6th.
- Phase 2 underground replacement work is underway and expected to be completed by mid-July.
- Concrete replacement, roadway work, and paving will follow.