June 12 Progress Update

  • Phase 1 (Dalebrooke and Broadway intersection) undergrounds and roadway work were 100% completed as of May 20th.
  • SaskEnergy completed the gas main relocation work on June 6th.
  • Phase 2 underground replacement work is underway and expected to be completed by mid-July.
  • Concrete replacement, roadway work, and paving will follow.