Deer Park Golf Course Clubhouse Project

Share on Facebook Share on Twitter Share on Linkedin Email this link

In 2019 the City of Yorkton conducted an Indoor Recreation Facility feasibility study with aodbt Architecture and Interior Design. In addition to the replacement of the Kinsmen Arena, the Deer Park Clubhouse was also identified as being a facility that has reached, or is nearing, the end of its useful life. After approving a general concept plan, and location for a possible new clubhouse at Deer Park at their October 26, 2020 Council meeting, City Council tasked Administration to work with aodbt Architecture and Interior Design to take the approved concept plan through to 100% design. The proposed new clubhouse includes water and sewer services as well.

Public questions and feedback were presented to Council, along with the final design and preliminary cost at the October 25, 2021 Council Meeting for Council consideration to decide whether to proceed to tender. The new Clubhouse was approved at the January 31, 2022 Council Meeting with a budget of $7.6 million.

The new Deer Park Clubhouse has a total capacity of 200 persons. This is when the restaurant, covered deck and patio are in use.

The breakdown is as follows:

  • Restaurant - 80 people
  • Covered deck - 80 people
  • Patio - 40 people

In 2019 the City of Yorkton conducted an Indoor Recreation Facility feasibility study with aodbt Architecture and Interior Design. In addition to the replacement of the Kinsmen Arena, the Deer Park Clubhouse was also identified as being a facility that has reached, or is nearing, the end of its useful life. After approving a general concept plan, and location for a possible new clubhouse at Deer Park at their October 26, 2020 Council meeting, City Council tasked Administration to work with aodbt Architecture and Interior Design to take the approved concept plan through to 100% design. The proposed new clubhouse includes water and sewer services as well.

Public questions and feedback were presented to Council, along with the final design and preliminary cost at the October 25, 2021 Council Meeting for Council consideration to decide whether to proceed to tender. The new Clubhouse was approved at the January 31, 2022 Council Meeting with a budget of $7.6 million.

The new Deer Park Clubhouse has a total capacity of 200 persons. This is when the restaurant, covered deck and patio are in use.

The breakdown is as follows:

  • Restaurant - 80 people
  • Covered deck - 80 people
  • Patio - 40 people
  • Clubhouse Progress Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Paving is complete! Landscaping work to start soon.
    Little details are coming together!

    The project completion is very near!


  • Clubhouse Progress Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Despite the rainy weather, paving has begun and is progressing well.


  • Clubhouse Progress Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Final details are coming together!






  • Clubhouse Progress Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    - North exterior is nearing completion
    - Interior restaurant is almost ready for flooring
    - Final touches being done to the back kitchen area
    - Display cabinets have been installed at main entrance
    - Bar area cabinetry is being installed
    - Pro Shop is open to the public


  • Clubhouse Progress Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The garage doors have been installed.

    These will open up access from the restaurant into the covered deck.


  • Clubhouse Progress Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Painting is underway in the restaurant
    • Women's washroom is nearing completion
    • Pro shop is getting the final touches installed
    • Getting ready for kitchen equipment

  • Clubhouse Progress Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Drywall boarding is almost complete in the lounge
    • 1st coat of paint in the lobby
    • Men’s washroom tiling is underway
    • Millwork in the pro-shop is moving along nicely






  • Clubhouse progress update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Drywall boarding is continuing nicely in the restaurant space.
    • Painting has begun in the lobby.
    • Tile is complete in Women’s and Family washroom’s
    • Millwork has begun in the pro-shop and workshop areas
    • Mechanical and electrical work is continuing nicely as well.


  • Clubhouse Progress Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The flooring in the Pro-Shop is complete!

    Tile is being installed in the women's and family washrooms and are near completion!

    Both covered and uncovered deck's sheathing is complete!






  • City Council Tour

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    On Wednesday, February 1st, 2023 the Mayor and Members of City Council had the opportunity to tour the new Deer Park Golf Course Clubhouse.

    Members of Council present for the tour included: Mayor Mitch Hippsley, Councillor Randy Goulden, Councillor Dustin Brears, Councillor Ken Chyz and Councillor Quinn Haider.