June 5, 2026 - Phase 1 Update

  • Phase 1 construction is underway. The recent unfavourable weather has caused some delays for Castle Construction.
  • Asphalt milling and concrete removal were completed on May 19th.
  • Phase 1 sanitary main replacement is approximately 80% complete.
  • Phase 1 water main and service (water and sanitary) replacements will follow over the next week.
  • SaskEnergy will be on site next week (weather delays pending) for approximately 3 days to replace the gas main across Dalebrooke Drive at the alley crossing south of Lakeview Road.