June 15, 2026 - Update

2026 Concrete Replacement Program

  • Northstar Concrete mobilized to Yorkton June 4th and began sawcutting and removals on York Road East (McBurney Drive to Mayhew Drive).
  • They will be working Monday to Friday and anticipate being in Yorkton for the next few months.
  • Removals will continue at multiple priority locations that overlap with the 2026 Asphalt Paving Program tomorrow.
  • The contractor returned to Yorkton on Monday, June 8th, and began replacements on York Road.


2026 Asphalt Paving Program

Fedorowich Construction plans to begin the mill and fill paving program June 30th.

  • June 30th - July 1st – Lawrence Avenue – service road /HW10 to Palliser Way
  • July 1stth – July 3rd - Yorkroad East – Mayhew Ave. to Cook Dr. / McBurney Dr.