July 27 - Schedule Update
2026 Asphalt Paving Program
- The project is approximately 10% completed.
- Fedorowich Construction completed milling and paving on York Road East (Mayhew Ave to McBurney Drive).
- July 27 - Milling and paving Collacott St W (Myrtle to Betts)
- July 27 – Milling and July 28 paving - Collacott St E (Second to Third)
- Henderson St W (Myrtle to First Ave N.) on July 28 milling – July 29th paving
- Wellington Avenue (Catherine to Darlington) – milling July 29 and paving on July 30th .
- Ball Road is now tentatively August 13th to 16th. This location will no longer be split into two phases. Milling would be completed on August 13th and 14th, with paving on the 15th and 16th.