July 20, 2026 - Schedule Update
The current 2026 Asphalt Paving Program schedule is as follows:
- York Road (Mayhew to McBurney) on July 20-23.
- Ball Road (Industrial to Ball Rd) north phase on July 25-26. The south phase is tentatively scheduled for August 15-16.
- Collacott St W (Myrtle to Betts) and Collacott St E (Second to Third) on July 27–28.
- Henderson St W (Myrtle to Betts) on July 28-29.
- Wellington Avenue (Catherine to Darlington) on July 29-30.
Fedorowich noted that this schedule is weather-dependent and may change if any roadway subgrade issues are encountered.