The current 2026 Asphalt Paving Program schedule is as follows:


  • York Road (Mayhew to McBurney) on July 20-23.
  • Ball Road (Industrial to Ball Rd) north phase on July 25-26. The south phase is tentatively scheduled for August 15-16.
  • Collacott St W (Myrtle to Betts) and Collacott St E (Second to Third) on July 27–28.
  • Henderson St W (Myrtle to Betts) on July 28-29.
  • Wellington Avenue (Catherine to Darlington) on July 29-30.


Fedorowich noted that this schedule is weather-dependent and may change if any roadway subgrade issues are encountered.