July 13, 2026 - Schedule Update
2026 Asphalt Paving Program
- July 13th Fedorowich Construction is on schedule to begin on Lawrence Avenue on Monday (July 13th). Milling and paving are scheduled to take 3 days.
- July 20th York Road (Mayhew Ave to McBurney Drive)
- July 23rd – Ball Road
- Collacot, Henderson and Dunlop to follow
Please note this plan is weather depending.
Thank you for your contribution!