August 28, 2026 - Update
2026 Concrete Replacement Program – (Northstar Concrete)
- The project is approximately 95% completed, (ahead of the 2026 & 2027 paving programs)
- Warranty work on Yorkroad and McBurney Dr. has started. Cracking in the curb & gutter and sidewalk replacements,
2026 Asphalt Paving Program – (Fedorowich Construction)
- The project is approximately 80% completed.
- Fedorowich plans to get back to this program the week of September 7th.