May 16, 2025 - Ozone Room

Preliminary work has begun with the removal of the decommissioned ozone tanks, along with associated piping and pumps.

The next phase of this project is scheduled to begin in July and will involve the full shutdown of the pool facility to accommodate construction.

Looking to your right of the room Looking to your left of the room
















Heading out the door! Headed to the Landfill.




















Empty and ready for construction.

Empty and ready for construction.