Getting Things Ready
With the existing sand filters and piping now out of the way, work has started on preparing for the new UV system and filter tanks. The doors and walls around the previous ozone room have been removed to provide better access for the UV system. New concrete pads to help support the new filters have also been framed, prepared, and poured. Lots of pipes and fitting are also going in, which are crucial to keeping the water moving throughout the entire system.
Outside of the back mechanical room, cleaning and organizing on deck and in programming areas is also happening. The guard room and equipment rooms have been cleared out ready for deep cleaning and paint, the water slide has been pressure washed before getting a fresh coat of wax. Tile walls in the pool tanks have been cleaned and are ready for some tile work to happen over the next few weeks.
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() | ||
![]() |
![]() |
|
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |