Making Progress

Work is continuing on the water park shutdown maintenance, in addition to the filtration and UV projects. A few maintenance items being worked on include:

  • Calcium removal from tile throughout the water park.
  • Skimmer cleaning and grouting.
  • Repairs to the wave generator air baffles (the system that makes the waves).
  • Rust removal and painting of the water slide structure.
  • Stripping and removal of old caulking on the water slide, preparing for buffing, waxing, and resealing the joints.
  • Deck drain flushing.
  • Remove, clean, and reseal drains in the lap pool.

For the filtration and UV project:

  • Three filter tanks have been placed.
  • Work started on required piping and valve replacement
  • Strainer baskets are being installed.